Key Construction Milestones

"..we want to make clear that our priority is and will be to ensure that the highest environmental and build standards are
duly implemented".

Ruben Casanova, Project Director

  • Preconstruction Activities: May – October 2017
  • North Breakwater: May 2017 – December 2019
  • Coast Road/St Fitticks Road re-alignment: October – November 2017
  • Closed Quays (with caissons) : June 2018 – April 2020
  • Open Quays (pile construction) : July 2018 – October 2019
  • South Breakwater: August 2018 – November 2019
  • Superstructure Works (buildings, etc): January 2019 – April 2020
  • M&E Works (including commissioning): March 2019 – April 2020
  • Delivery of Project: May 2020
     